Demolition works begin at Belfast shipyard in preparation for warship build

Demolition work commences buildings at H&W in Belfast as the shipyard prepares for the FSS warship building programme
Demolition work commences buildings at H&W in Belfast as the shipyard prepares for the FSS warship building programme

DEMOLITION work has begun at the iconic Harland & Wolff site on Belfast's Queen's Island to mark the start of a journey to becoming the UK’s most technologically advanced shipyard.

Following the award of the manufacturing subcontract with Navantia in relation to the £1.6 billion FSS warship programme, H&W confirmed it would see the £77 million invested in technology in its Belfast and Appledore shipyards.

An extension to the fabrication halls will be undertaken to facilitate a highly dynamic material and sub-structure production flow along with a highly efficient manufacturing and production process.

Investments will be made in technologically advanced robotic and autonomous equipment that includes material movement, marking, plate cutting, panel lines and robotic welding. In addition, new larger paint buildings will be constructed to facilitate larger and more efficient block painting.

This subcontract will be a significant and historic step change to Harland and Wolff’s capabilities and will make it an important participant in the international shipbuilding industry, specifically with modern shipyards and a proven track record post FSS.

Following the planned investments and upgrades to its sites, Harland & Wolff will be able to capitalise on further multi-billion-pound fabrication and heavy engineering opportunities within the defence, renewables and commercial maritime markets globally.

The business will target a significant number of floating offshore wind projects for which fabrication is expected to commence between 2024 and 2030.

The FSS Warship programme will last seven years and bring long term employment and opportunities until 2031.

Harland & Wolff will be responsible for the fabrication of various blocks including some mega blocks (ie, a block incorporating several standard sized blocks) as well as the procurement of a number of items of equipment to be installed on each vessel in Belfast.

Given the experience its Appledore shipyard has in the fabrication of the bow sections for the Queen Elizabeth Class aircraft carriers – HMS Queen Elizabeth and the Prince of Wales, all three bow sections for this programme will be fabricated there, prior to being transported to Belfast.

All three vessels will have all the blocks assembled, consolidated, fully integrated and commissioned before proceeding to sea trials from the Belfast facility, marking a return to shipbuilding in Belfast after over 20 years.

Full scale fabrication is due to commence in 2025 with the vessels due to be delivered to meet the Ministry of Defence’s objective to bring three ships into service by 2032.